Helical Pier Installation
 |
Laying out the steel piers and loading up the project as per Design Support Plans by Proffessional Engineer. |
 |
Holding two basement levels in place and supported, while excavating. |
Piers are installed 28 feet below grade. Holding this block wall of the garage during the backfilling of the excavation. |
 |
 |
Install 8 X 8 Angle Steel supports with foundation clips |
 |
Install Foundation Clips and Angle Steel Supports, Grout, and Seal with Asphalt paint for further Corriosn and Water Proof Protection. |
 |
As you can see, you only get one chance to install the piers right. These piers where drilled in to 28 feet below grade, in order to support the house during the soil remediation. Looking up is the bottom of the poured foundation, FABCO excavated 16 feet below grade and 25 feet in under the house. |
 |
FABCO excavated the impacted soil and cleaned up the project, the helical piers supported the house all though the soil remediation, with no prolblems. FABCO leaves the helical piers in the ground for continued support forever. The piers are hot dipped galvanized and will last 100 years without coating. FABCO coated the ones above to protect the foundation wall water proofing.
|
 |
Foundation support piers columns filled with concrete neat mix. |
|
|
|